Master Plan Update - November 2019

 

Progress is continuing to be made on the new stadium. The home-side bleachers have been installed and crews are completing the final punch list items. The away bleachers will not be installed until after the demolition of the existing high school.

The stadium field is being prepped for the installation of the field turf. Weather permitting - the turf installation should be completed within 60 days.

The track layout has been installed and the primary base paving has been completed. The final finished surface will not be installed until the spring, once the weather is warmer.

The building roof installation is nearing completion and window installation is underway and making progress.

The majority of the interior wall studding has been completed and drywall installation has commenced followed by painting.

The winter goal is to have the building weather-tight by the end of January.