Master Plan Update October 7, 2019
Master Plan Update October 7, 2019

Crews worked hard this summer to accomplish the many projects that needed to be completed prior to the start of school.

Summer Activities

  • Blue gym was demolished to allow for the installation of the new stadium. The demolition was completed in the beginning of August.
  • The South Rolling Road expansion project was completed by the end of August. Portions of South Rolling Road will now allow for pedestrian traffic and parallel parking on both sides of the street.
  • The rework of Speakman Drive was completed. Speakman Drive was reopened for student traffic by the beginning of the school year.

The building continues to make progress. The primary focus this Fall, is to complete the roof installation and installing the windows throughout the building. The goal is to have the building weather-tight by end of December. Work crews will continue to work on the installation of the stadium throughout the fall and winter months.

To see more pictures, click here.